  • Second phase of an engineering study is under way for MRT extension to Johor

    20 Jul 2016

    |

    1,858 views

    A project to extend the Thomson-East Coast Line north into Johor Bahru is gaining traction, with the second phase of an advanced engineering study under way.


    A project to extend the Thomson-East Coast Line north into Johor Bahru is gaining traction, with the second phase of an advanced engineering study under way. In response to queries from The Straits Times, Singapore's Ministry of Transport said the study will take up to the second quarter of 2018 to complete. But it could be completed by the third quarter of next year, it said. Both Singapore and Johor launched the joint study in April.

    "Phase two is intended to develop the detailed engineering design for the rapid transit system project," a ministry spokesman said.

    The Straits Times understands that this stage of the study will include a detailed look at the feasibility, merits and cost-effectiveness of various alignments, number of stops and whether the straits crossing will be made under the sea or via a bridge.

    The project was first announced in 2010 by Prime Minister Lee Hsien Loong and his Malaysian counterpart Najib Razak. The Land Transport Authority (LTA) said then that the cross-border rapid transit project would be an extension of the Thomson-East Coast Line, and would be completed by 2018. This was pushed to 2019 when Singapore decided to lengthen the Thomson-East Coast Line.

    Since then, there had been little progress reported on the 4-5km extension, with Singapore saying it was waiting for Johor to decide on the location of its terminal station.

    But last August, Malaysia confirmed that the station terminus would be in Bukit Chagar, just north of JB Sentral. The Bukit Chagar terminus will have its own customs and immigration facilities, according to the New Straits Times. Separately, the LTA said it embarked on a ridership study of the Singapore-Johor Bahru extension last month.

    It said the study is expected to be completed by the end of the year. Construction industry watchers said the line is unlikely to be completed before 2020.
    24.4k

    Tags

    mrt thomson east coast line mass rapid transport lta land transport authority

    AllReviewsNewsAdviceFeaturesVideos
    • Home
    • Car Articles
    • news
    • news Listings
    • LTA News

    Second phase of an engineering study is under way for MRT extension to Johor

    20 Jul 2016

    |

    1,858 views

    A project to extend the Thomson-East Coast Line north into Johor Bahru is gaining traction, with the second phase of an advanced engineering study under way.


    A project to extend the Thomson-East Coast Line north into Johor Bahru is gaining traction, with the second phase of an advanced engineering study under way. In response to queries from The Straits Times, Singapore's Ministry of Transport said the study will take up to the second quarter of 2018 to complete. But it could be completed by the third quarter of next year, it said. Both Singapore and Johor launched the joint study in April.

    "Phase two is intended to develop the detailed engineering design for the rapid transit system project," a ministry spokesman said.

    The Straits Times understands that this stage of the study will include a detailed look at the feasibility, merits and cost-effectiveness of various alignments, number of stops and whether the straits crossing will be made under the sea or via a bridge.

    The project was first announced in 2010 by Prime Minister Lee Hsien Loong and his Malaysian counterpart Najib Razak. The Land Transport Authority (LTA) said then that the cross-border rapid transit project would be an extension of the Thomson-East Coast Line, and would be completed by 2018. This was pushed to 2019 when Singapore decided to lengthen the Thomson-East Coast Line.

    Since then, there had been little progress reported on the 4-5km extension, with Singapore saying it was waiting for Johor to decide on the location of its terminal station.

    But last August, Malaysia confirmed that the station terminus would be in Bukit Chagar, just north of JB Sentral. The Bukit Chagar terminus will have its own customs and immigration facilities, according to the New Straits Times. Separately, the LTA said it embarked on a ridership study of the Singapore-Johor Bahru extension last month.

    It said the study is expected to be completed by the end of the year. Construction industry watchers said the line is unlikely to be completed before 2020.
    24.4k

    Tags

    mrt thomson east coast line mass rapid transport lta land transport authority

    Newsletter

    Be Notified On The Latest News

    Newsletter

    Be Notified On The Latest News

    Latest COE Prices

    October 2026 | 1st BIDDING
    NEXT TENDER: 21 Oct 2026
    CAT A
    $130,001
    CAT B
    $130,100
    CAT C
    $91,889
    CAT E
    $137,000
    default status
    View Full Results

    Latest COE Prices

    October 2026 | 1st BIDDING
    NEXT TENDER: 21 Oct 2026
    CAT A
    $130,001
    CAT B
    $130,100
    CAT C
    $91,889
    CAT E
    $137,000
    default status
    View Full Results

    You May Also Like

    Sgcarmart Explores: Bras Basah!

    Sgcarmart Explores: Bras Basah!

    New cars are safer: Opt for one when you can

    New cars are safer: Opt for one when you can

    Leapmotor B10: The electric SUV focused on what matters

    Leapmotor B10: The electric SUV focused on what matters

    LTA sets up poll to decide the least-ugliest EV plate

    LTA sets up poll to decide the least-ugliest EV plate

    Cars of 2026

    Cars of 2026

    Inside Foton's commercial vehicle range in Singapore

    Inside Foton's commercial vehicle range in Singapore

    The all new XPENG Mona L03 is one smart coupe SUV

    The all new XPENG Mona L03 is one smart coupe SUV

    Sgcarmart Explores: East Coast Park!

    Sgcarmart Explores: East Coast Park!

    Must-Have Car Accessories Every EV Driver Should Own

    Must-Have Car Accessories Every EV Driver Should Own

    Opinion: Why do we even need green number plates?

    Opinion: Why do we even need green number plates?

    Hongqi Singapore opens its showroom doors

    Hongqi Singapore opens its showroom doors

    BYD Sealion 8 DM-i Review

    BYD Sealion 8 DM-i Review

    BYD Atto 3 Evo Facelift Review

    BYD Atto 3 Evo Facelift Review

    Don't get yourself trapped in your high-tech EV

    Don't get yourself trapped in your high-tech EV

    iCaur V23 100kW Review

    iCaur V23 100kW Review

    The BYD Sealion 8 seven-seater SUV arrives in Singapore

    The BYD Sealion 8 seven-seater SUV arrives in Singapore

    You May Also Like

    Sgcarmart Explores: Bras Basah!

    Sgcarmart Explores: Bras Basah!

    New cars are safer: Opt for one when you can

    New cars are safer: Opt for one when you can

    Leapmotor B10: The electric SUV focused on what matters

    Leapmotor B10: The electric SUV focused on what matters

    LTA sets up poll to decide the least-ugliest EV plate

    LTA sets up poll to decide the least-ugliest EV plate

    Cars of 2026

    Cars of 2026

    Inside Foton's commercial vehicle range in Singapore

    Inside Foton's commercial vehicle range in Singapore

    The all new XPENG Mona L03 is one smart coupe SUV

    The all new XPENG Mona L03 is one smart coupe SUV

    Sgcarmart Explores: East Coast Park!

    Sgcarmart Explores: East Coast Park!

    Must-Have Car Accessories Every EV Driver Should Own

    Must-Have Car Accessories Every EV Driver Should Own

    Opinion: Why do we even need green number plates?

    Opinion: Why do we even need green number plates?

    Hongqi Singapore opens its showroom doors

    Hongqi Singapore opens its showroom doors

    BYD Sealion 8 DM-i Review

    BYD Sealion 8 DM-i Review

    BYD Atto 3 Evo Facelift Review

    BYD Atto 3 Evo Facelift Review

    Don't get yourself trapped in your high-tech EV

    Don't get yourself trapped in your high-tech EV

    iCaur V23 100kW Review

    iCaur V23 100kW Review

    The BYD Sealion 8 seven-seater SUV arrives in Singapore

    The BYD Sealion 8 seven-seater SUV arrives in Singapore

    Related Articles

    Hongqi E-HS9 Review

    Hongqi E-HS9 Review

    MGS5 Luxury vs Aion V Luxury

    MGS5 Luxury vs Aion V Luxury

    Big Test: Which brand makes the best hybrid?

    Big Test: Which brand makes the best hybrid?

    The all new XPENG Mona L03 is one smart coupe SUV

    The all new XPENG Mona L03 is one smart coupe SUV

    Hyundai details Elexio electric SUV for Singapore

    Hyundai details Elexio electric SUV for Singapore

    Inside Foton's commercial vehicle range in Singapore

    Inside Foton's commercial vehicle range in Singapore

    Cars of 2026

    Cars of 2026

    Potential fixes to our COE system

    Potential fixes to our COE system

    Related Articles

    Hongqi E-HS9 Review

    Hongqi E-HS9 Review

    MGS5 Luxury vs Aion V Luxury

    MGS5 Luxury vs Aion V Luxury

    Big Test: Which brand makes the best hybrid?

    Big Test: Which brand makes the best hybrid?

    The all new XPENG Mona L03 is one smart coupe SUV

    The all new XPENG Mona L03 is one smart coupe SUV

    Hyundai details Elexio electric SUV for Singapore

    Hyundai details Elexio electric SUV for Singapore

    Inside Foton's commercial vehicle range in Singapore

    Inside Foton's commercial vehicle range in Singapore

    Cars of 2026

    Cars of 2026

    Potential fixes to our COE system

    Potential fixes to our COE system