Some SMRT staff own up to lapses during 'amnesty'
04 Nov 2017|1,328 views
Staff from at least one department in SMRT have admitted to lapses in their work, in response to a company call to own up - without penalty - before a wide-scale audit is launched. The Straits Times understands that the employees are from SMRT's building and facilities department, which oversees areas such as MRT tunnel ventilation, and flood and fire protection measures at train stations.
The offer was made to quickly establish the extent of improper practices, and to allow staff to 'volunteer information in open reporting as a mitigation against further disciplinary action', SMRT's Group Chief Executive Desmond Kuek said in a statement on Thursday evening. SMRT has told staff that it will embark on a massive audit and inspection exercise following the amnesty period, and lapses uncovered will be dealt with.
These measures follow revelations that SMRT staff responsible for maintaining the pumps of a storm water pit at Bishan station had signed off on work that was not done. It is suspected that the falsification of the quarterly maintenance records went as far back as December last year. The manager and staff responsible have been suspended and are assisting in investigations. SMRT also replaced its Vice President of Maintenance a week after the flooding.
Observers said SMRT's amnesty offer is a rare move, and held mixed views on its effectiveness. Mr. William Thien, a Principal Consultant at EON Consulting and Training, said, "It's a good effort to identify potential gaps quickly, calling on the conscience of employees to do the right thing." "Giving amnesty is not a common thing in companies. But given that SMRT is providing a public good, which has a great impact on public transport, I can understand why," Mr. Thien added. He said organisations mostly rely on whistle-blowing channels to bring up lapses.
PeopleWorldwide Consulting's Managing Director David Leong said, "From an HR perspective, it's very poor people management. The trust between the management and staff is totally lost. "It doesn't lead anywhere... Are you going to retain the people who owned up and let them do the same job? Or are you enticing them to come out, to remove them later?"
Staff from at least one department in SMRT have admitted to lapses in their work, in response to a company call to own up - without penalty - before a wide-scale audit is launched. The Straits Times understands that the employees are from SMRT's building and facilities department, which oversees areas such as MRT tunnel ventilation, and flood and fire protection measures at train stations.
The offer was made to quickly establish the extent of improper practices, and to allow staff to 'volunteer information in open reporting as a mitigation against further disciplinary action', SMRT's Group Chief Executive Desmond Kuek said in a statement on Thursday evening. SMRT has told staff that it will embark on a massive audit and inspection exercise following the amnesty period, and lapses uncovered will be dealt with.
These measures follow revelations that SMRT staff responsible for maintaining the pumps of a storm water pit at Bishan station had signed off on work that was not done. It is suspected that the falsification of the quarterly maintenance records went as far back as December last year. The manager and staff responsible have been suspended and are assisting in investigations. SMRT also replaced its Vice President of Maintenance a week after the flooding.
Observers said SMRT's amnesty offer is a rare move, and held mixed views on its effectiveness. Mr. William Thien, a Principal Consultant at EON Consulting and Training, said, "It's a good effort to identify potential gaps quickly, calling on the conscience of employees to do the right thing." "Giving amnesty is not a common thing in companies. But given that SMRT is providing a public good, which has a great impact on public transport, I can understand why," Mr. Thien added. He said organisations mostly rely on whistle-blowing channels to bring up lapses.
PeopleWorldwide Consulting's Managing Director David Leong said, "From an HR perspective, it's very poor people management. The trust between the management and staff is totally lost. "It doesn't lead anywhere... Are you going to retain the people who owned up and let them do the same job? Or are you enticing them to come out, to remove them later?"