  • $344m overhaul of Bukit Panjang LRT, smoother rides expected from 2022

    07 Mar 2018

    |

    1,167 views

    Commuters can expect more reliable rides on the Bukit Panjang LRT from 2022, when the majority of its $344 million overhaul is expected to be completed.


    Commuters using the Bukit Panjang LRT (BPLRT) can expect more reliable rides from 2022, when the majority of works to overhaul the problematic line is completed. The Government on Wednesday (7th March) gave details of the $344 million renewal project for the 19-year old system that it has awarded to the original supplier of the system, Bombardier.

    Key milestones of the BPLRT renewal project
    "The BPLRT... is reaching the end of its useful life," said Transport Minister Khaw Boon Wan during the debate on his ministry's budget.

    Since it opened in 1999, the 14-station BPLRT has been dogged by reliability issues, owing to how its design comprises sharp turns over undulating terrain.

    In the first three quarters of last year, there were six delays on the BPLRT that were longer than 30 minutes.

    The renewal project, which will start in the first half of this year, will cover the upgrade of the line's existing signalling system with a more precise Communications-Based Train Control (CBTC) system which has better control of train speeds.

    The new system also has more redundancy - meaning that in the event of faults, the system will have back-ups to keep trains running. The power rail along the entire 7.8km-long BPLRT will also be replaced and more robust power rail brackets will be installed.

    The 19 trains, which have been in service since the BPLRT was launched will also be replaced with new ones that will have better propulsion motors, eco-friendly LED lights and better air-conditioning systems. 13 trains, which have been in service since 2015, will also be upgraded.

    The Land Transport Authority (LTA) said the new CBTC, trains and power rail system will also be equipped with condition monitoring features, to oversee the life cycle of the systems, so predictive maintenance can be scheduled.


    Bukit Panjang LRT Station was closed on 12th January after a train damaged a signal stop tape
    The new signalling system and new trains will be fully rolled out by 2022, while others works such as the replacement of the power rail, and decommissioning of the old signalling system's track circuits should be completed by 2024.

    The LTA said that while most of the works will be completed during off-service hours, where required, the BPLRT's operating hours will be shortened to provide engineers with more time.

    To create additional space for the upgrading works, one of three routes of the BPLRT, Service C, which connects to Ten Mile Junction station, will stop operating permanently from the fourth quarter of this year.

    This means that commuters have to take a bus to that station from Bukit Panjang station. The remaining 13 stations will continue to be accessible via Services A and B.

    LTA's Deputy Chief Executive for Infrastructure and Development, Mr. Chua Chong Kheng, said that Bombardier's proposal met the authority's specifications, as it does not require any modification to existing rail infrastructure and minimal disruption to services and commuters.

    Bombardier is also 'familiar with the current system', said LTA, and has also been involved in ongoing reliability work carried out since 2016. The manufacturer will also provide a new service support arrangement where Bukit Panjang LRT operator SMRT will engage Bombardier through a long-term maintenance contract for spares, training and technical expertise.
    24.4k

    Tags

    mrt smrt lrt bukit panjang bukit panjang lrt bukit panjang lrt breakdown mrt breakdown mrt delay

    AllReviewsNewsAdviceFeaturesVideos
    • Home
    • Car Articles
    • news
    • news Listings
    • MRT News

    $344m overhaul of Bukit Panjang LRT, smoother rides expected from 2022

    07 Mar 2018

    |

    1,167 views

    Commuters can expect more reliable rides on the Bukit Panjang LRT from 2022, when the majority of its $344 million overhaul is expected to be completed.


    Commuters using the Bukit Panjang LRT (BPLRT) can expect more reliable rides from 2022, when the majority of works to overhaul the problematic line is completed. The Government on Wednesday (7th March) gave details of the $344 million renewal project for the 19-year old system that it has awarded to the original supplier of the system, Bombardier.

    Key milestones of the BPLRT renewal project
    "The BPLRT... is reaching the end of its useful life," said Transport Minister Khaw Boon Wan during the debate on his ministry's budget.

    Since it opened in 1999, the 14-station BPLRT has been dogged by reliability issues, owing to how its design comprises sharp turns over undulating terrain.

    In the first three quarters of last year, there were six delays on the BPLRT that were longer than 30 minutes.

    The renewal project, which will start in the first half of this year, will cover the upgrade of the line's existing signalling system with a more precise Communications-Based Train Control (CBTC) system which has better control of train speeds.

    The new system also has more redundancy - meaning that in the event of faults, the system will have back-ups to keep trains running. The power rail along the entire 7.8km-long BPLRT will also be replaced and more robust power rail brackets will be installed.

    The 19 trains, which have been in service since the BPLRT was launched will also be replaced with new ones that will have better propulsion motors, eco-friendly LED lights and better air-conditioning systems. 13 trains, which have been in service since 2015, will also be upgraded.

    The Land Transport Authority (LTA) said the new CBTC, trains and power rail system will also be equipped with condition monitoring features, to oversee the life cycle of the systems, so predictive maintenance can be scheduled.


    Bukit Panjang LRT Station was closed on 12th January after a train damaged a signal stop tape
    The new signalling system and new trains will be fully rolled out by 2022, while others works such as the replacement of the power rail, and decommissioning of the old signalling system's track circuits should be completed by 2024.

    The LTA said that while most of the works will be completed during off-service hours, where required, the BPLRT's operating hours will be shortened to provide engineers with more time.

    To create additional space for the upgrading works, one of three routes of the BPLRT, Service C, which connects to Ten Mile Junction station, will stop operating permanently from the fourth quarter of this year.

    This means that commuters have to take a bus to that station from Bukit Panjang station. The remaining 13 stations will continue to be accessible via Services A and B.

    LTA's Deputy Chief Executive for Infrastructure and Development, Mr. Chua Chong Kheng, said that Bombardier's proposal met the authority's specifications, as it does not require any modification to existing rail infrastructure and minimal disruption to services and commuters.

    Bombardier is also 'familiar with the current system', said LTA, and has also been involved in ongoing reliability work carried out since 2016. The manufacturer will also provide a new service support arrangement where Bukit Panjang LRT operator SMRT will engage Bombardier through a long-term maintenance contract for spares, training and technical expertise.
    24.4k

    Tags

    mrt smrt lrt bukit panjang bukit panjang lrt bukit panjang lrt breakdown mrt breakdown mrt delay

    Newsletter

    Be Notified On The Latest News

    Newsletter

    Be Notified On The Latest News

    Latest COE Prices

    September 2026 | 1st BIDDING
    NEXT TENDER: 23 Sep 2026
    CAT A
    $133,009
    CAT B
    $135,001
    CAT C
    $93,101
    CAT E
    $137,890
    View Full Results

    Latest COE Prices

    September 2026 | 1st BIDDING
    NEXT TENDER: 23 Sep 2026
    CAT A
    $133,009
    CAT B
    $135,001
    CAT C
    $93,101
    CAT E
    $137,890
    View Full Results

    You May Also Like

    EV NEXT: Peace of mind with battery SOH certification

    EV NEXT: Peace of mind with battery SOH certification

    New to driving? Here's how to become a better driver

    New to driving? Here's how to become a better driver

    Away from the hustle and bustle with Aion owners

    Away from the hustle and bustle with Aion owners

    Get your next rental from AKA Car Rental

    Get your next rental from AKA Car Rental

    Hongqi E-HS9 Review

    Hongqi E-HS9 Review

    Honda's 'Super Numbers' turn heads and win hearts

    Honda's 'Super Numbers' turn heads and win hearts

    Dunlop's new tyres for an electrified world

    Dunlop's new tyres for an electrified world

    Porsche Cayenne Electric Review

    Porsche Cayenne Electric Review

    You May Also Like

    EV NEXT: Peace of mind with battery SOH certification

    EV NEXT: Peace of mind with battery SOH certification

    New to driving? Here's how to become a better driver

    New to driving? Here's how to become a better driver

    Away from the hustle and bustle with Aion owners

    Away from the hustle and bustle with Aion owners

    Get your next rental from AKA Car Rental

    Get your next rental from AKA Car Rental

    Hongqi E-HS9 Review

    Hongqi E-HS9 Review

    Honda's 'Super Numbers' turn heads and win hearts

    Honda's 'Super Numbers' turn heads and win hearts

    Dunlop's new tyres for an electrified world

    Dunlop's new tyres for an electrified world

    Porsche Cayenne Electric Review

    Porsche Cayenne Electric Review

    Related Articles

    LTA's CRL3 will connect Jurong Lake District to Gul Circle

    LTA's CRL3 will connect Jurong Lake District to Gul Circle

    LTA to host special public preview of three new stations

    LTA to host special public preview of three new stations

    Catch your free MRT ride between three Circle Line stations!

    Catch your free MRT ride between three Circle Line stations!

    LTA to build new MRT station on North-South Line

    LTA to build new MRT station on North-South Line

    LTA to spruce up MRT stations for its 30th anniversary

    LTA to spruce up MRT stations for its 30th anniversary

    Public transport fares to increase by up to 5%

    Public transport fares to increase by up to 5%

    LTA taskforce appoints Independent Advisory Panel

    LTA taskforce appoints Independent Advisory Panel

    LTA to close Simei and Tanah Merah MRT stations for 10 days

    LTA to close Simei and Tanah Merah MRT stations for 10 days

    Related Articles

    LTA's CRL3 will connect Jurong Lake District to Gul Circle

    LTA's CRL3 will connect Jurong Lake District to Gul Circle

    LTA to host special public preview of three new stations

    LTA to host special public preview of three new stations

    Catch your free MRT ride between three Circle Line stations!

    Catch your free MRT ride between three Circle Line stations!

    LTA to build new MRT station on North-South Line

    LTA to build new MRT station on North-South Line

    LTA to spruce up MRT stations for its 30th anniversary

    LTA to spruce up MRT stations for its 30th anniversary

    Public transport fares to increase by up to 5%

    Public transport fares to increase by up to 5%

    LTA taskforce appoints Independent Advisory Panel

    LTA taskforce appoints Independent Advisory Panel

    LTA to close Simei and Tanah Merah MRT stations for 10 days

    LTA to close Simei and Tanah Merah MRT stations for 10 days