Stage 2 of Thomson-East Coast line delayed by six months until Q3 2021
15 Dec 2020|1,446 views
A signalling fault that disrupted train services on the Thomson-East Coast MRT Line (TEL) on 4 December 2020 has contributed to a delay in the opening of Stage 2 of the line.
It has been pushed back by another six months till the third quarter of 2021 for a more thorough review of the rail system software, said the Land Transport Authority (LTA) on 14 December 2020. In addition, other major rail and road infrastructure projects are also facing delays of up to a year because of the COVID-19 pandemic, it added in a statement.


A major cause of the delay is the suspension of work during the eight-week circuit breaker period, which ended on 1 June 2020. Other factors cited by the LTA include disruptions to the global supply chain for construction materials and a general manpower crunch owing to border closures.
It said the revised completion and opening timelines for these projects are still being finalised, and it will issue updates in due course. Explaining the delay in Phase 2 of the TEL, the LTA said, "The recent disruption of TEL prompted LTA to review the software of the system, which contributed to the delay, more thoroughly with our contractor.
"As rail systems are complex, it is better that we try to iron out as many teething issues as possible before opening the next phase. This is a key reason why TEL is being opened in phases." The signalling problem disrupted train services between Woodlands North and Woodlands South stations for more than five hours in the morning, including the peak hours.


This latest delay is the second setback for TEL's Phase 2, which involves six stations from Springleaf to Caldecott. The first was a three month-delay, with the completion date pushed from the end of this year to the first quarter of 2021.
On Monday, the LTA said construction has progressively resumed at all its work sites since 2 June 2020. "Our contractors have been adhering to strict safe management measures at work sites, including mandatory daily temperature monitoring, using SafeEntry or TraceTogether to check in and out, as well as ensuring work is carried out in groups of no more than five workers with no inter-mingling between groups."
The chairman of the Transport Government Parliamentary Committee, Mr Saktiandi Supaat, told The Straits Times on Monday the delay is "understandable". It is important to have a thorough review of the system and software to ensure things are done properly before the next phase of the TEL is rolled out, he said.


The Government will expand the MRT network significantly from around 230km today to 360km by the early 2030s. This includes opening the remaining stages of the TEL, Circle Line Stage 6, the North East Line extension, Jurong Region Line and Cross Island Line.
Originally slated to be completed by 2024, the TEL will span 43km and serve about 500,000 commuters daily in its initial years. It is Singapore's sixth MRT line, with a total of 32 new stations, including eight interchange stations.
The Circle Line 6 extension, originally slated to be operational in 2025, will add three stations between HarbourFront and Marina Bay MRT stations.
Phase 1 of the Cross Island Line, which will serve residential and industrial areas such as Loyang, Tampines, Pasir Ris, Defu, Hougang, Serangoon North and Ang Mo Kio, was to be completed by 2029. As for the North-South Corridor, it was slated to be ready by end-2026 before COVID-19 forced the delay.
A signalling fault that disrupted train services on the Thomson-East Coast MRT Line (TEL) on 4 December 2020 has contributed to a delay in the opening of Stage 2 of the line.
It has been pushed back by another six months till the third quarter of 2021 for a more thorough review of the rail system software, said the Land Transport Authority (LTA) on 14 December 2020. In addition, other major rail and road infrastructure projects are also facing delays of up to a year because of the COVID-19 pandemic, it added in a statement.


A major cause of the delay is the suspension of work during the eight-week circuit breaker period, which ended on 1 June 2020. Other factors cited by the LTA include disruptions to the global supply chain for construction materials and a general manpower crunch owing to border closures.
It said the revised completion and opening timelines for these projects are still being finalised, and it will issue updates in due course. Explaining the delay in Phase 2 of the TEL, the LTA said, "The recent disruption of TEL prompted LTA to review the software of the system, which contributed to the delay, more thoroughly with our contractor.
"As rail systems are complex, it is better that we try to iron out as many teething issues as possible before opening the next phase. This is a key reason why TEL is being opened in phases." The signalling problem disrupted train services between Woodlands North and Woodlands South stations for more than five hours in the morning, including the peak hours.


This latest delay is the second setback for TEL's Phase 2, which involves six stations from Springleaf to Caldecott. The first was a three month-delay, with the completion date pushed from the end of this year to the first quarter of 2021.
On Monday, the LTA said construction has progressively resumed at all its work sites since 2 June 2020. "Our contractors have been adhering to strict safe management measures at work sites, including mandatory daily temperature monitoring, using SafeEntry or TraceTogether to check in and out, as well as ensuring work is carried out in groups of no more than five workers with no inter-mingling between groups."
The chairman of the Transport Government Parliamentary Committee, Mr Saktiandi Supaat, told The Straits Times on Monday the delay is "understandable". It is important to have a thorough review of the system and software to ensure things are done properly before the next phase of the TEL is rolled out, he said.


The Government will expand the MRT network significantly from around 230km today to 360km by the early 2030s. This includes opening the remaining stages of the TEL, Circle Line Stage 6, the North East Line extension, Jurong Region Line and Cross Island Line.
Originally slated to be completed by 2024, the TEL will span 43km and serve about 500,000 commuters daily in its initial years. It is Singapore's sixth MRT line, with a total of 32 new stations, including eight interchange stations.
The Circle Line 6 extension, originally slated to be operational in 2025, will add three stations between HarbourFront and Marina Bay MRT stations.
Phase 1 of the Cross Island Line, which will serve residential and industrial areas such as Loyang, Tampines, Pasir Ris, Defu, Hougang, Serangoon North and Ang Mo Kio, was to be completed by 2029. As for the North-South Corridor, it was slated to be ready by end-2026 before COVID-19 forced the delay.