MRT tunnel flooding entirely preventable, says LTA report
06 Dec 2017|1,144 views
The flooding of the tunnel near Bishan MRT station on 7th October was 'entirely preventable' had SMRT carried out proper maintenance, the Land Transport Authority (LTA) said yesterday when it unveiled the findings of its investigation. Rail operator SMRT said it accepted full responsibility for the incident in which floodwaters reached up to a metre in depth in train tunnels and led to a section of the North-South Line being shut down for 14.5 hours. The shutdown affected 231,000 commuters.


Three storm water sump pumps - each capable of removing 85 litres of water per second - at Bishan station were also found to be in working condition, as they could still be activated manually following the incident. The LTA said that the flood protection measures were 'more than adequate' to handle the 7th October rainfall.
"The storm water sump pit has a capacity of 5,044m3, which is much more than the estimated 640m3 of rainfall that was cleared from the tunnels between Bishan and Braddell MRT stations," an LTA spokesman said, adding that the flood protection measures have a 'huge buffer'. Further STS laboratory tests found three possible reasons the system failed to prevent the flooding.
One was that the lowest float switch, which would have activated the storm water sump pumps, could have been obstructed by accumulated silt and sludge in the pit. Another was that floating debris in the pit could have impeded the normal functioning of the float switches - in particular, the highest float switch, which alerts the SMRT Operations Control Centre to high water levels.


"Nonetheless, all three possible failure scenarios could only arise as a result of a lack of proper maintenance, audits and supervision," it added, noting that silt, sludge and debris had to be cleared from the pit after the incident. The LTA added that SMRT had also made 'numerous engineering enhancements to improve the robustness and resilience of flood protection measures' at Bishan station and other tunnel portals to further reduce the risk of a recurrence.
These include replacing the pumps at Bishan station with more durable ones that can handle water with sediment, and installing an extra set of parallel float switches and a radar-based sensor system to monitor water levels . A new pump control panel - accessible to maintenance staff even during passenger train services - has also been installed, said SMRT Corporate Communications Vice President Patrick Nathan.
He added that all non-serviceable pumps on the North-South and East-West Lines had been replaced following checks, with float switches also replaced as a precaution. While extra measures may help, improving the culture of maintenance is more important than adding 'safeguard after safeguard', said Mr. Chong Kee Sen, former President of the Institution of Engineers, Singapore. He added that in any organisation, it is important for top management to engage with maintenance teams to boost their morale and ensure they understand the importance of their work.
The flooding of the tunnel near Bishan MRT station on 7th October was 'entirely preventable' had SMRT carried out proper maintenance, the Land Transport Authority (LTA) said yesterday when it unveiled the findings of its investigation. Rail operator SMRT said it accepted full responsibility for the incident in which floodwaters reached up to a metre in depth in train tunnels and led to a section of the North-South Line being shut down for 14.5 hours. The shutdown affected 231,000 commuters.


Officers from the Singapore Civil Defence Force, PUB, LTA and SMRT worked through the night on 7th October to clear the water in the flooded tunnel
Three storm water sump pumps - each capable of removing 85 litres of water per second - at Bishan station were also found to be in working condition, as they could still be activated manually following the incident. The LTA said that the flood protection measures were 'more than adequate' to handle the 7th October rainfall.
"The storm water sump pit has a capacity of 5,044m3, which is much more than the estimated 640m3 of rainfall that was cleared from the tunnels between Bishan and Braddell MRT stations," an LTA spokesman said, adding that the flood protection measures have a 'huge buffer'. Further STS laboratory tests found three possible reasons the system failed to prevent the flooding.
One was that the lowest float switch, which would have activated the storm water sump pumps, could have been obstructed by accumulated silt and sludge in the pit. Another was that floating debris in the pit could have impeded the normal functioning of the float switches - in particular, the highest float switch, which alerts the SMRT Operations Control Centre to high water levels.


"Nonetheless, all three possible failure scenarios could only arise as a result of a lack of proper maintenance, audits and supervision," it added, noting that silt, sludge and debris had to be cleared from the pit after the incident. The LTA added that SMRT had also made 'numerous engineering enhancements to improve the robustness and resilience of flood protection measures' at Bishan station and other tunnel portals to further reduce the risk of a recurrence.
These include replacing the pumps at Bishan station with more durable ones that can handle water with sediment, and installing an extra set of parallel float switches and a radar-based sensor system to monitor water levels . A new pump control panel - accessible to maintenance staff even during passenger train services - has also been installed, said SMRT Corporate Communications Vice President Patrick Nathan.
He added that all non-serviceable pumps on the North-South and East-West Lines had been replaced following checks, with float switches also replaced as a precaution. While extra measures may help, improving the culture of maintenance is more important than adding 'safeguard after safeguard', said Mr. Chong Kee Sen, former President of the Institution of Engineers, Singapore. He added that in any organisation, it is important for top management to engage with maintenance teams to boost their morale and ensure they understand the importance of their work.
Latest COE Prices
June 2025 | 2nd BIDDING
NEXT TENDER: 09 Jul 2025
CAT A$98,124
CAT B$116,670
CAT C$65,000
CAT E$116,889
View Full Results Thank You For Your Subscription.