MRT rides on North-South Line set to be faster after sleepers are replaced
25 Apr 2015|1,970 views
Work to replace sleepers on the North-South Line (NSL) will be completed by the end of this month, and commuters can expect faster train rides when speed restrictions are lifted, said the Land Transport Authority (LTA) and rail operator SMRT in a joint statement today, reported The Straits Times.
During the works, trains had to travel at slower speeds of around 40-60km/h on some stretches for safety. With the completion of works, trains will now travel at about 80km/h, shortening journey times by around 10 to 15 percent, the statement added. For example, the ride from Jurong East to Marina Bay will take about 67 minutes, compared to about 77 minutes when speed restrictions were imposed.
With works on the NSL nearing completion, sleeper replacement on the East-West Line (EWL) will start from mid-May this year. In total, more than 92,000 timber sleepers between Boon Lay and Tiong Bahru, and between Lavender and Pasir Ris, will be replaced with concrete sleepers. Works are expected to be completed by end 2016.
SMRT has started to apply temporary speed restrictions at stretches of the EWL as part of preliminary track works, which will increase total end-to-end travel time by about 10 minutes. Portable acoustic screens will be installed at work sites to reduce noise, and train services may also end earlier at certain stations on the EWL during the works.
The sleeper replacement programme is part of an effort to improve commuter experience on the two lines.
Work to replace sleepers on the North-South Line (NSL) will be completed by the end of this month, and commuters can expect faster train rides when speed restrictions are lifted, said the Land Transport Authority (LTA) and rail operator SMRT in a joint statement today, reported The Straits Times.
During the works, trains had to travel at slower speeds of around 40-60km/h on some stretches for safety. With the completion of works, trains will now travel at about 80km/h, shortening journey times by around 10 to 15 percent, the statement added. For example, the ride from Jurong East to Marina Bay will take about 67 minutes, compared to about 77 minutes when speed restrictions were imposed.
With works on the NSL nearing completion, sleeper replacement on the East-West Line (EWL) will start from mid-May this year. In total, more than 92,000 timber sleepers between Boon Lay and Tiong Bahru, and between Lavender and Pasir Ris, will be replaced with concrete sleepers. Works are expected to be completed by end 2016.
SMRT has started to apply temporary speed restrictions at stretches of the EWL as part of preliminary track works, which will increase total end-to-end travel time by about 10 minutes. Portable acoustic screens will be installed at work sites to reduce noise, and train services may also end earlier at certain stations on the EWL during the works.
The sleeper replacement programme is part of an effort to improve commuter experience on the two lines.